# Budget a job: contracts, change orders and committed costs

Before a job starts, two numbers matter: the **contract**, what the customer agreed to pay, and the **budget**, what you expect the work to cost you. The gap between them is the profit you planned.

When the work changes, a **change order** is the customer's signed agreement to a new price, and it moves the budget with it. As the job runs, cost moves through three stages: **committed** (ordered from a vendor or sub on a purchase order or subcontract), **actual** (billed to you), and **projected** (where the job will land). Watching projected cost against the budget tells you a job is running over while there's still time to act.

|| Adding contracts, budgets and change orders needs Business Max and the owner or bookkeeper role. Anyone who can open the project can read them. Projects themselves are explained in [Track job costs with Projects](https://help.booksgpt.ai/en/article/track-job-costs-with-projects-1bcfxd5/).

## Add the contract

Go to the job: open **All pages** in the left sidebar, then click **Sales** and **Projects**, and click the job.

1. Under the job's figures, click **Add a contract**.
2. Choose how:
   - **From an estimate**: pick an accepted estimate for the project's customer. The contract is the estimate's amount before tax, and the budget is built from each line's cost.
   - **Type it**: enter the **Contract amount** and **Contract date**, and add the budget afterwards.
3. Click **Make it the contract** (or **Save contract**).

You can also click **Make it the contract** on an accepted estimate itself.

| On the estimate, fill in each line's **Cost**, what that work costs you, before making it the contract. Only the owner and bookkeeper see it, and it never appears on anything the customer receives.

Making an estimate the contract locks it, so the price you agreed can't drift, and that contract changes only through change orders. To bill it, click **Invoice the contract**: BooksGPT drafts one invoice for the original contract.

## Set or change the budget

Open the job's **Budget** tab. If there's no budget yet, pick one of three ways in:

- **From an estimate**: makes the contract and the budget in one step.
- **Import a file**: a spreadsheet from any estimating app. Check the columns BooksGPT matched (line, cost type, amount), pick the date it starts, and import.
- **Type it**: one line per cost type, each with an amount.

Every change saves a new **version** with the date it starts. Earlier versions stay, so a report for an earlier date shows the budget you had then. To change it later, click **New version** or **Import budget**. To look back, pick a version from the **Version** list.

With cost codes, each budget line can carry one too. Set up your list in [Settings](https://app.booksgpt.ai/go/settings) under **Sales & projects**, then **Cost codes**, starting from a ready-made list such as **Residential** or your own file.

## Change orders: a signed change to the contract

1. On the job's **Change orders** tab, click **New change order**.
2. Fill in **What changes**, the **Date** and the **Contract change** before tax. For a credit to the customer, enter a negative amount.
3. Under **Budget lines**, add what the change does to your budget, by cost type.
4. Click **Send to sign**, then send the email. Or click **Copy link instead** and send the link yourself.

The customer opens the link, types their full name, ticks the box and taps **Approve**, or declines.

![Change order 2 on a phone, with Approve and Decline](https://img.booksgpt.ai/help/job-budgets/change-order-phone.png)

Only an approved change order changes anything. From the day the customer approves it:

- The contract goes up (or down) by the change.
- The budget gets a new version with the change order's lines added.

A draft, one waiting for a signature, a declined one and a void one change nothing.

![Change orders tab: one waiting, one approved](https://img.booksgpt.ai/help/job-budgets/change-orders-tab.png)

- **Changed the budget first?** If you saved budget versions after the contract, the Change orders tab offers **Make a change order**, which turns those edits into one for the customer to sign.
- **Edited one after sending it?** Send it again. The customer signs the new version, not the old one.
- **Billing.** **Invoice the contract** covers the original contract only. Bill each approved change order on its own invoice.
- **An approved change order stands.** To reverse it, make a new change order with a negative amount.

## Track committed and projected cost

The **Budget** tab lists each cost type with its budget lines under it:

- **Original**: the budget in effect, approved change orders included.
- **Committed**: what you've ordered for that line on purchase orders and subcontracts. Hover it to see each order and how much is still open, not billed yet.
- **Actual**: the cost billed or paid so far.
- **Projected**: where the cost will land. Normally the larger of the budget, or the cost so far plus what's still open on order.
- **To complete**: projected minus the cost so far.
- **Variance**: budget minus actual. Below zero means over budget.

![Budget tab with Committed, Projected, Order and Forecast](https://img.booksgpt.ai/help/job-budgets/budget-committed-projected.png)

To commit cost straight from the budget:

1. On a budget line, click **Order**.
2. A new purchase order opens with the job, the cost type and what's left on the line filled in. A Subcontractors line opens a **Subcontract**, which is measured in dollars instead of quantities.
3. Pick the vendor and save.

When the vendor's bill for that order is posted with **Save & post**, its amount stops being open and counts as actual cost. A draft bill doesn't count yet.

To tell BooksGPT more about a line, click **Forecast** and pick one:

- **Final**: no more cost is coming, so projected is the cost so far.
- **Estimate at completion**: your own figure for the line's whole cost.
- **Open**: back to the normal rule.

Projected and To complete always count from the job's start on the accrual basis, whatever the page shows.

## See every job at once

Open **All pages**, then click **Reports** and **Job cost**. **All jobs** shows each job's contract, budget, committed, cost, projected cost, variance, income and profit. Pick one job to see it by cost type. **Export** saves it as Excel or CSV.

## If something goes wrong

**The budget from an estimate is too low.** Some estimate lines had no cost. Add the costs and save a new budget version, by typing it or importing a file.

**A change order didn't change the contract.** The customer hasn't approved it yet. On the **Change orders** tab, open its ⋯ menu and use **Send to sign** or **Copy link** to send it again.

**Committed looks too high.** An order is still open for work that's finished or called off. Bill what's due, then click **Close** on the order, or **Cancel order** if nothing was billed.

**There's no Add a contract button.** You need the owner or bookkeeper role, and the workspace needs Business Max.